Projects

Saturday, April 3, 2010

First floor walls



After months of site work, ductwork, concrete work and shoveling snow the framing seems a breeze.

The finished deck

Sleepers and Mudsills


Pressure treated sleepers and mudsills were installed over the slab so subflooring and wood floors can be installed later.

Second Pour for House


The second pour encases the ductwork within a thermal mass of concrete. Warm water and an accelerant was used in the concrete mix due to winter temperatures.

Completing the ductwork




The completed ductwork. Wire mesh placed to strengthen the slab.

HVAC Trunk Line

The homes forced air system will pass a series of ductwork through the slab creating a "heat energy battery". In this image 8" round ductwork is being tied into the central trunk line.
A high compressive strength foam board was at point loads and bearing wall locations. The foil faced insulation board, which has a greater R-value was used everywhere else.
Electrical conduits were run to the home's load center. The conduits will be allow future access to the panel without disturbing the thermal envelope.

First Concrete Pour

The first pour goes down in a level two inch layer to provide an anchoring surface for the ductwork that will follow.

Under Slab Insulation

Here the forms are up, the vapor barrier has been placed, and two layer of rigid foam are being installed prior to the first concrete pour. The foam is fit tightly with staggered joints and taped seams.